Agenda Item #36


Item Title
C-39 Schematic/Preliminary/Final (Phase I, II & III) Plans and Specifications for Orange Park High School Smoke Corridor Building 1, Phases I and II

Issue/Rationale

Each phase or combination of phases is submitted to the School Board for review and approval.  The plans have received staff review and are complete to Schematic/ Preliminary/Final stage.

 

 



Recommended Action

Approve the Plans and Specifications.



Financial Impact

The Architect’s construction cost estimate is $275,930.00.  The District’s budget for this project is $220,000.00.



Submitted By

James A. Connell, Assistant Superintendent for Support Services