Agenda Item #31


Item Title
C-32 Clay High School Duct Board Replacement Building 3A Substantial and Final Completion

Issue/Rationale

Establish Substantial and Final Completion dates formally for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. These dates are determined by the Project Manager in accordance with Project documents. Substantial Completion was achieved on July 18, 2007 and Final Completion was achieved on August 1, 2007.

 

The project, as determined by the Project Manager and Project Engineer (Kenyon & Partners, Inc.), has achieved Substantial and Final Completion in accordance with the project documents. Liquidated damages are specified in the contract; therefore, substantial and final completion dates must be formally established.

 

 

 

 



Recommended Action

Approve Substantial Completion as submitted effective, July 18, 2007.

Approve Final Completion as submitted effective, August 1, 2007.



Financial Impact

None



Submitted By

Thomas L. Smith, Director of Maintenance & Operations