School District of Clay County Green Cove Springs, Florida |
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway Hearings for Special Actions regarding Students - 4:00 p.m. REGULAR MEETING - 7:00 p.m. |
Agenda Item #32 Item Title C-34 Change Order #3 for Middleburg High School Chiller Replacement (Revised) Issue/Rationale Change orders are initiated by the Contractor, Architect/Engineer or Owner, which may increase or decrease the scope of the project as defined by the plans and specifications. Once a change order is initiated, review/evaluation is undertaken to determine the merit and/or requirements of the change order. Change orders affect the scope of the project and are required to be School Board approved by State Requirements for Educational Facilities and Florida Statutes.
Recommended Action Approve Change Order #3 as submitted Financial Impact None Submitted By Thomas L. Smith, Director of Maintenance & Operations Attachment: CO3.MHS.Chiller.pdf |