School District of Clay County Green Cove Springs, Florida |
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway Hearings for Special Actions regarding Students - 4:00 p.m. REGULAR MEETING - 7:00 p.m. |
Agenda Item #35 Item Title C-37 Middleburg High School Chiller Replacement Substantial Completion (Revised) Issue/Rationale Establish a Substantial Completion date formally for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. This date is determined by the Project Manager in accordance with Project documents. Substantial Completion was achieved on July 28, 2006. The project, as determined by the Project Manager and Project Engineer (Kenyon & Partners, Inc.), is substantially complete and in accordance with the project documents. Liquidated damages are specified in the contract; therefore, a substantial completion date must be formally established. Recommended Action Approve Substantial Completion as submitted. Financial Impact None. Submitted By Thomas L. Smith, Director of Maintenance & Operations Attachment: SC.MHS.Chiller.pdf |