Agenda Item #36 Item Title C-38 Doctors Inlet Elementary Parking Improvements Substantial Completion (Revised) Issue/Rationale Establish a Substantial Completion date formally for audit purposes, and as required by the State Requirements for Educational Facilities and
The project, as determined by the Project Manager and Project Engineer (Mittauer & Associates, Inc.), is substantially complete and in accordance with the project documents. Liquidated damages are specified in the contract; therefore, a substantial completion date must be formally established.
Recommended Action Approve Substantial Completion Financial Impact None Submitted By James A. Connell, Director of Facility Planning and Construction Attachment: DIS Sub. Comp..pdf |