Agenda Item #38


Item Title
C-38 Additive Change Order #3 for Orange Park High School HVAC Roof Top Unit Replacement Building 1

Issue/Rationale

Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications.  Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board.  This change order is to identify 100 zone damper locations not shown on the as-built drawings.  Contractor:  Weather Engineers, Inc.; Engineer:  KPI Engineering, Inc.

 



Recommended Action

Approve the change order.



Financial Impact

If approved, this Change Order will increase the contract amount by $4,048.64.  The substantial completion date is August 5, 2011.  Engineer fees will increase by $242.92 as a result of this Change Order.



Submitted By

James A. Connell, Assistant Superintendent for Support Services

 

Data Source:

Mike Griffis, Facility Planning and Construction