School District of Clay County
Green Cove Springs, Florida
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway Hearings for Special Actions regarding Students - 4:00 p.m. REGULAR MEETING - 7:00 p.m.
August 18, 2011 Regular Meeting
Agenda Item #43


Item Title
C-43 Additive Change Order #2 (Days Only) for Wilkinson Junior High School Lightning Protection System

Issue/Rationale

Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications.  Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board.  This change order is required to add days to the contract due to the shop drawings for this project being delayed pending approval of an alternate lightning protection system.   Contractor:  T & M Electric, Inc.; Engineer:  KPI Engineering, Inc. 



Recommended Action

Approve the change order.



Financial Impact

If approved, this Change Order will add thirty (30) additional days to the contract.



Submitted By

James A. Connell, Assistant Superintendent for Support Services

 

Data Source:

Mike Griffis, Facility Planning and Construction




Attachment:  CO 2 WJH Lightning Protection.pdf