Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway Hearings for Special Actions regarding Students - 4:00 p.m. REGULAR MEETING - 7:00 p.m. |
Agenda Item #40 Item Title C-40 Substantial Completion of Montclair Elementary School Panelboard Replacement Buildings 1 – 3 Issue/Rationale Establish a Substantial Completion date formally for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. Substantial Completion was achieved on July 31, 2011. This phase of the project, as determined by the Project Manager and Project Engineer (KPI Engineering, Inc.), is substantially complete and in accordance with the project documents. Contractor: Parks Electric Service, Inc. Recommended Action Approve Substantial Completion. Financial Impact None Submitted By James A. Connell, Assistant Superintendent for Support Services Data Source: Mike Griffis, Facility Planning and Construction Attachment: Sub Compl MCE Panelboards.pdf |