Item Title
C-35 Additive Change Order #1 for Clay High School Building 5 HVAC Replacement

Issue/Rationale

Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications.  Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board.  This change order is required to add a mezzanine access ladder and furnish and install breakers.  Contractor:  W. W. Gay Mechanical Contractor, Inc.; Engineer:  KPI Engineering, Inc.  

  



Recommended Action

Approve the change order.



Financial Impact

If approved, this Change Order will increase the contract amount by $5,736.00.  The substantial completion date was July 29, 2010.  Architect fees will increase by $344.16 as a result of this Change Order.