C-32 (Connell) Additive Change Order 1 for Clay High School Building 2 Duct Board Replacement (Phase III)

Issue/Rationale

Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications.  Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board.  Change order Items 1 and 4-8 were requested by the Code Enforcement Department to bring the building up to current codes.  Items 2 and 3 were requested by the Facilities Planning and Construction Department to complete all ceiling replacement in Building 2.  Contractor:  Bill Williams Air Conditioning and Heating, Inc.; Engineer:  KPI Engineering, Inc.      



Recommended Action

Approve the change order.



Financial Impact

If approved, this Change Order will increase the contract amount by $9,369.84.  The substantial completion date is August 14, 2009.  Engineer fees will increase by $562.19  as a result of this Change Order.

 



Submitted By

James A. Connell, Director of Facility Planning and Construction