Agenda Item #43 Item Title C-43 Substantial Completion of District Ancillary Facility Blanding Entry Phase Issue/Rationale Establish a Substantial Completion date formally for audit purposes, and as required by the State Requirements for Educational Facilities and
The project, as determined by the Project Manager and Project Architect (Bhide & Hall Architects, P.A.), is substantially complete and in accordance with the project documents. Liquidated damages are specified in the contract; therefore, a substantial completion date must be formally established. Recommended Action Approve Substantial Completion Financial Impact None Submitted By James A. Connell, Director of Facility Planning and Construction Attachment: Substantial Completion District Ancillary Blanding Entry.pdf |