August 21, 2014 - Regular Meeting
Agenda Item #56


Item Title
C-61 Substantial Completion of Orange Park High School Roof Replacement Building 4

Issue/Rationale

Establish a Substantial Completion date for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes.  The project, as determined by the Project Manager and Project Architect, has reached Substantial Completion in accordance with the project documents on August 7, 2014. 



Recommended Action

Approve Substantial Completion

 



Financial Impact

None



Submitted By

John C. Merrill, Assistant Superintendent for Support Services




Attachment:  Sub Comp OPH Roof Replacement.pdf