Agenda Item #41


Item Title
C-43 Schematic/Preliminary/Final (Phase I, II & III) Plans and Specifications for Keystone Heights High School HVAC Replacement Building 1

Issue/Rationale

Each phase or combination of phases is submitted to the School Board for review and approval.  The plans have received staff review and are complete to Schematic/Preliminary/Final (Phase I, II & III) stage.

 



Recommended Action

Approve the Plans and Specifications.



Financial Impact

The Engineer’s construction cost estimate is $200,000.  The District budget for this project is $200,000.



Submitted By

John C. Merrill, Assistant Superintendent for Support Services