Agenda Item #39


Item Title
C-39 Final (Phase III) Plans and Specifications for Orange Park Elementary School, Building 4 Re-Roof

Issue/Rationale

Each phase or combination of phases is submitted to the School Board for review and approval.  School Board approval is required in order to move to the next phase and/or submit to the Building Department for plan review and approval.  The plans have received staff review and are complete to Final (Phase III) stage.



Recommended Action
Approve Orange Park Elementary School, Building 4 Re-Roof Final Plans and Specifications.

Financial Impact
The District’s construction cost estimate is $79,559.00.

Submitted By

James A. Connell, Director of Facility Planning and Construction