School District of Clay County Green Cove Springs, Florida |
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway Hearings for Special Actions regarding Students - 4:00 p.m. REGULAR MEETING - 7:00 p.m. |
Agenda Item #30 Item Title C-29 Substantial Completion of Middleburg Elementary School Building 1 Remodel Issue/Rationale Establish a Substantial Completion date for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. The project, as determined by the Project Manager and Project Architect (McCullar & Boatright Architects, P.A.), has reached Substantial Completion in accordance with the project documents on January 20, 2012. Recommended Action Approve Substantial Completion Financial Impact None Submitted By James A. Connell, Assistant Superintendent for Support Services Data Source: Mike Griffis, Facility Planning and Construction Attachment: MBE Bldg 1 Remodel Substantial Completion.pdf |