School District of Clay County
Green Cove Springs, Florida
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway Hearing for Special Actions Regarding Students - 3:30 p.m. REGULAR MEETING - 7:00 p.m.
February 19, 2009 Regular Meeting
Agenda Item #28


Item Title
C-28 Additive Change Order #1 (Days Only) to Install an Additional Chiller at Ridgeview High School

Issue/Rationale

Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of as defined by the plans and specifications. Once a Change Order is initiated, review/evaluation is undertaken to determine the merit and/or requirement of the Change Order. Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board. Change Orders affect the scope of the project (see attached summary) and are required to be School Board by State Requirements for Educational Facilities and Florida Statutes.

 

Contractor: AC General, Inc.; Engineer: Estrella Engineering Incorporated



Recommended Action
Approve the Change Order as submitted.

Financial Impact
N/A

Submitted By
Thomas L. Smith, Director of Maintenance


Attachment:  CO 1 Days Only.pdf