School District of Clay County
Green Cove Springs, Florida
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway Hearings for Special Actions regarding Students - 4:00 p.m. REGULAR MEETING - 7:00 p.m.
February 21, 2013 - Regular Meeting
Agenda Item #26


Item Title
Substantial Completion of Orange Park High School Renovation/Remodel West Campus – Phase II

Issue/Rationale

Establish a Substantial Completion date for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes.  The project, as determined by the Project Manager and Project Architect (McCullar & Boatright Architects, P.A.), has reached Substantial Completion in accordance with the project documents on January 18, 2013.                   



Recommended Action

Approve Substantial Completion



Financial Impact

None



Submitted By

James A. Connell, Assistant Superintendent for Support Services

 

Data Source:

 

Mike Griffis, Facility Planning and Construction




Attachment:  OPHS Renovate.Remodel West Campus Substantial Completion.pdf