School District of Clay County
Green Cove Springs, Florida
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway FEBRUARY 16, 2006 HEARINGS FOR SPECIAL ACTIONS REGARDING STUDENTS - 4:00 PM REGULAR MEETING - 7:00 PM
February Regular Meeting
Agenda Item #26


Item Title
Substantial Completion of Clay Hill Elementary, Phase III

Issue/Rationale

Establish a Substantial Completion date formally for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. This date is determined by the Project Manager in accordance with project documents.  Substantial Completion was achieved on December 14, 2005.

                                                                                   

The project, as determined by the Project Manager and Project Architect (Gibraltar Design), is substantially complete and in accordance with the project documents. Liquidated damages are specified in the contract; therefore, a substantial completion date must be formally established.



Recommended Action

Approve Substantial Completion.



Financial Impact
None.

Submitted By

James A. Connell, Director of Facility Planning and Construction




Attachment:  Substantial Completion CHE.pdf