School District of Clay County
Green Cove Springs, Florida
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway JANUARY 18, 2007 Hearings for Special Actions regarding Students - 4:00 p.m. Regular Meeting - 7:00 p.m.
January 18, 2007 Regular Meeting
Agenda Item #33


Item Title
C-32 Deductive Change Order #1 (Direct Purchasing) for Charles E. Bennett Elementary Classroom Replacement

Issue/Rationale

Direct purchasing change orders are almost always deductive and are the sole initiative of the owner.  These change orders represent the purchase of materials and/or equipment directly by the School Board in order to save the sales tax.  The direct purchases are deducted from the original contract in the form of a change order.  Change orders affect the scope of the project and are required to be School Board approved.  Contractor:  M M Parrish Construction Company; Architect:  Bhide & Hall Architects P.A.         



Recommended Action

Approve the change order.



Financial Impact

This deduction from the construction contract in the amount of $977,210.61 will not impact the budget.  A total tax savings in the amount of $56,304.37 is realized as a result of this direct purchasing change order.



Submitted By

James A. Connell, Director of Facility Planning and Construction




Attachment:  Change Order 1, CEB.pdf