Agenda Item #36 Item Title C-37 Final (Phase III) Plans and Specifications for Montclair Elementary School Panelboard Replacement Buildings 1-3 Issue/Rationale Each phase or combination of phases is submitted to the School Board for review and approval as required by State Requirements for Educational Facilities and Florida Statutes. The plans have received staff review and are complete to the Final (Phase III) stage. The Final Plans are on file within the Facility Planning and Construction Department. Engineer: KPI Engineering, Inc. Recommended Action Approve the plans. Financial Impact The cost estimate is $76,282.00. Submitted By Michael J. Elliott, Assistant Superintendent of Support Services Data Source: Facility Planning and Construction |