Agenda Item #3


Item Title
Review 2010-11 (Initial Year) Tentative Educational Facilities Plan

Issue/Rationale
The Board will receive summary documents on the revenue and planned project initiatives for FY 2010-11.  Tentative approval of project initiatives and estimated expenditures for FY 2010-11 are required and will be scheduled for July 26, 2010.  The complete long range tentative Educational Facilities Plan, as required by Florida Statutes, will be presented at the August 19, 2010 Regular School Board meeting.  Final approval is scheduled for the September 16, 2010 Special School Board meeting.

Recommended Action
Receive and review 2010-11 (Initial Year) Tentative Educational Facilities Plan, ask any questions, and prepare to revise or approve on July 26, 2010.

Financial Impact
Estimates of project costs are identified within the Plan.