C-56 Additive Change Order #2 for Clay High School Building 1 Duct Board Replacement (Phase IV)

Issue/Rationale

Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications.  Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board for approval.  The additive changes are for the replacement of non-working portable air conditioning unit in the concession room with a new split system.



Recommended Action
Approve the Change Order.

Financial Impact
If approved, this Change Order will increase the contract amount by $12,900.00.  The Substantial Completion date is July 30, 2010.  Final Completion date is August 15, 2010.  Architect fees will increase by $774.00 as a result of this change order.

Submitted By

Michael J. Elliott, Assistant Superintendent of Support Services

 

Data Source:

 

Facility Planning and Construction




Attachment:  CO 2 CHS Bldg 1 Duct Board Replacement.pdf