Agenda Item #37


Item Title
C-36 Charles E. Bennett Elementary School Substantial Completion

Issue/Rationale

Establish a Substantial Completion date formally for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. Substantial Completion was achieved on June 18, 2007.

 

This phase of the project, as determined by the Project Manager and Project Architect (Bhide & Hall Architects, P.A.), is substantially complete and in accordance with the project documents. Liquidated damages are specified in the contract; therefore, a substantial completion date must be formally established.  Contractor:  M. M. Parrish Construction.



Recommended Action

Approve Substantial Completion.



Financial Impact

None



Submitted By

James A. Connell, Director of Facility Planning and Construction




Attachment:  Substantial Completion, CEB Ph I Construction.pdf