Agenda Item #32 Item Title C-32 Substantial Completion of Orange Park High School Renovation/Remodel West Campus – Phase I Issue/Rationale Establish a Substantial Completion date for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. The project, as determined by the Project Manager and Project Architect (McCullar & Boatright Architects, P.A.), has reached Substantial Completion in accordance with the project documents on June 14, 2012. Recommended Action Approve Substantial Completion Financial Impact None Submitted By James A. Connell, Assistant Superintendent for Support Services Data Source: Mike Griffis, Facility Planning and Construction Attachment: OPHS West Campus Ph I Substantial Completion.pdf |