Agenda Item #38 Item Title C-39 Final Completion of Orange Park High School Roof Replacement Building 4 (Gymnasium) Issue/Rationale Establish a Final Completion date formally for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. The Final Completion date was June 1, 2011. This phase of the project, as determined by the Project Manager and Project Architect/Engineer McCullar & Boatright Architects, P.A., is finally complete and in accordance with the project documents. Contractor: J. Register Company, Inc. Recommended Action Approve Final Completion Financial Impact None Submitted By James A. Connell, Assistant Superintendent for Support Services Data Source: Mike Griffis, Facility Planning and Construction Attachment: Final Compl OPH Gym Roof.pdf |