School District of Clay County Green Cove Springs, Florida |
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway Hearings for Special Actions regarding Students - 2:30 p.m. REGULAR MEETING - 7:00 P.M. |
Agenda Item #37 Item Title C-38 Final Completion of District Office Roof Replacement H.C. Long Buildings 1-5 Issue/Rationale Establish a Final Completion date formally for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. The Final Completion date was June 10, 2011. This phase of the project, as determined by the Project Manager and Project Architect/Engineer McCullar & Boatright Architects, P.A., is finally complete and in accordance with the project documents. Contractor: Halbert Contracting Company, Inc. Recommended Action Approve Final Completion Financial Impact None Submitted By James A. Connell, Assistant Superintendent for Support Services Data Source: Mike Griffis, Facility Planning and Construction Attachment: Final Compl HC Long Roof Replace.pdf |