Agenda Item #42


Item Title
C-43 Deductive Change Order #1 (Direct Purchasing) for S. Bryan Jennings Elementary School Buildings 4-9 Re-Roof

Issue/Rationale

Direct purchasing change orders are almost always deductive and are the sole initiative of the owner.  These change orders represent the purchase of materials and/or equipment directly by the School Board in order to save the sales tax.  The direct purchases are deducted from the original contract in the form of a change order.  Change orders affect the scope of the project and are required to be School Board approved.  Contractor:  Childers Roofing & Sheet Metal, Inc.; Architect:  McCullar & Boatright Architects, P.A.

 



Recommended Action

Approve the change order.



Financial Impact

A total tax savings in the amount of $3,846.45 is realized as a result of this direct purchasing change order.



Submitted By

James A. Connell, Director of Facility Planning and Construction




Attachment:  CO 1, SBJ.pdf