School District of Clay County Green Cove Springs, Florida |
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway MARCH 15, 2007 Hearings for Special Actions regarding Students - 4:00 p.m. REGULAR MEETING - 7:00 p.m. |
Agenda Item #31 Item Title C-32 Change Order #11 for Coppergate Elementary School Issue/Rationale Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications. Once a Change Order is initiated, review/evaluation is undertaken to determine the merit and/or requirement of the Change Order. Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board. Change Orders affect the scope of the project (see attached summary) and are required to be School Board approved by State Requirements for Educational Facilities and Florida Statutes. Contractor: Thomas May Construction Company; Architect: Bhide & Hall Architects, P.A.
Recommended Action Approve the Change Order as presented. Financial Impact If approved, this Change Order will increase the contract amount by $16,602.96. The substantial completion date is March 2, 2007. Architect fees will increase by $651.73 as a result of this Change Order. Submitted By James A. Connell, Director of Facility Planning and Construction Attachment: Change Order 11, CGE.pdf |