School District of Clay County Green Cove Springs, Florida |
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway MAY 17, 2007 Hearings for Special Actions regarding Students - 4:00 p.m. Regular Meeting - 7:00 p.m. |
Agenda Item #48 Item Title C-47 Final (Phase III) Plans and Specifications for Chiller Replacement at Lake Asbury Elementary School Issue/Rationale Final (Phase III) Plans and Specifications are required to have School Board approval prior to the submission to the Code Enforcement Department for plan review. The Final Plans and Specifications are on file within the Department of Maintenance and Operations. Recommended Action Approve the Final (Phase III) Plans and Specifications as submitted. Financial Impact Part IV Capital Outlay will be used to fund this project. $140,000.00 has been budgeted for the project in the 5-Year Capital Projects Plan. Submitted By Thomas L. Smith, Director of Maintenance & Operations |