School District of Clay County Green Cove Springs, Florida |
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway Hearings for Special Actions regarding Students - 3:00 p.m. REGULAR MEETING - 7:00 p.m. |
Agenda Item #35 Item Title C-34 Additive Change Order #6 for Orange Park High School Renovate/Remodel West Campus Issue/Rationale Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications. Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board for approval. The additive changes are for owner requested items (see attached). Recommended Action Approve the Change Order. Financial Impact If approved, this Change Order will increase the contract amount by $44,697.30. The Substantial Completion date for Phase I is June 14, 2012. Final Completion date for Phase I is July 15, 2012. Contract Substantial Completion date for Phase II is January 23, 2013. Final Completion date for Phase II is February 22, 2013. Architect fees will increase by $2,681.82 as a result of this change order. Submitted By James A. Connell, Assistant Superintendent for Support Services Data Source: Mike Griffis, Facility Planning and Construction Attachment: CO6 OPHS Renovate.Remodel West Campus.pdf |