School District of Clay County
Green Cove Springs, Florida
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway Hearings for Special Actions regarding Students - 3:00 p.m. REGULAR MEETING - 7:00 p.m.
May 17, 2012 Regular Meeting
Agenda Item #35


Item Title
C-34 Additive Change Order #6 for Orange Park High School Renovate/Remodel West Campus

Issue/Rationale

Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications.  Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board for approval.  The additive changes are for owner requested items (see attached).



Recommended Action

Approve the Change Order.



Financial Impact

If approved, this Change Order will increase the contract amount by $44,697.30.  The Substantial Completion date for Phase I is June 14, 2012.  Final Completion date for Phase I is July 15, 2012.  Contract Substantial Completion date for Phase II is January 23, 2013.  Final Completion date for Phase II is February 22, 2013.  Architect fees will increase by $2,681.82 as a result of this change order.



Submitted By

James A. Connell, Assistant Superintendent for Support Services

 

Data Source:

 

Mike Griffis, Facility Planning and Construction




Attachment:  CO6 OPHS Renovate.Remodel West Campus.pdf