Agenda Item #40 Item Title C-39 Substantial and Final Completion of Lakeside Elementary School Lighting Issue/Rationale Establish a Substantial and Final Completion date for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. The project, as determined by the Project Manager and Project Architect, has reached Substantial Completion in accordance with the project documents on April 7, 2016. Final Completion was achieved on May 10, 2016. Recommended Action Approve Substantial and Final Completion Financial Impact None Submitted By John C. Merrill, Assistant Superintendent for Support Services Attachment: LES Lighting Substantial and Final.pdf |