School District of Clay County
Green Cove Springs, Florida
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway November 21, 2006 - Immediately following the 7:00 p.m. Reorganization Meeting
November 21, 2006 REGULAR MEETING
Agenda Item #35


Item Title
C-29 (Bolla) Final Completion of Oakleaf School

Issue/Rationale

Establish a Final Completion date formally for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. This date is determined by the Project Manager in accordance with project documents.  The Final Completion date for Buildings 1-4 is September 4, 2006 and the Final Completion date for Building 5 and the Athletic Field’s is October 28, 2006.

                                                                                   

The project, as determined by the Project Manager and Project Architect (JRA Architects), has reached final completion in accordance with the project documents. Liquidated damages are specified in the contract; therefore, a final completion date must be formally established. 

                                                                        

 

 

 

 

 

 

 

 

 

 

 

 



Recommended Action
Approve Final Completion as submitted.

Financial Impact
None

Submitted By
James A. Connell, Director of Facility Planning and Construction


Attachment:  Final Completion OLS.pdf