Agenda Item #36


Item Title
C-35 Final Completion of Ridgeview Elementary School Chiller Replacement and Air Handling Unit Replacement Buildings 1 & 3

Issue/Rationale

Establish a Final Completion date for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. Final Completion was achieved on November 4, 2011.  The project, as determined by the Project Manager and Project Engineer (KPI Engineering, Inc.), has reached Final Completion in accordance with the project documents.



Recommended Action

Approve Final Completion



Financial Impact

None



Submitted By

James A. Connell, Assistant Superintendent for Support Services

 

Data Source:

 

Mike Griffis, Facility Planning and Construction




Attachment:  RVE Bldgs 1 & 3 Final Completion.pdf