Agenda Item #26


Item Title
C-26 Additive Change Order #9 for OakLeaf High School

Issue/Rationale

Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications.  Once a Change Order is initiated, review/evaluation is undertaken to determine the merit and/or requirement of the Change Order.  Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board for approval.  The additive changes are required for eighteen items that were requested by the district and two items that were code/safety issues.

 

                 

 

 



Recommended Action
Approve the Change Order.

Financial Impact
If approved, this Change Order will increase the contract amount by $247,184.32.  The Substantial Completion date is June 1, 2010.  Final Completion date is June 29, 2010.  Architect fees will increase by $12,359.22 as a result of this change order.