Item Title
C-43 Final Completion of Clay High School A/C Duct Board Replacement

Issue/Rationale

Establish a Final Completion date formally for audit purposes, and as required by the State Requirements for Education Facilities and Florida Statutes. This date is determined by the Project Manager in accordance with Project documents. Final Completion was achieved on September 3, 2008.

 

The project, as determined by the Project Manager and Project Engineer (Kenyon & Partners, Inc.), has achieved Final Completion in accordance with the project documents. Liquidated damages are specified in the contract; therefore, a Final Completion date must be formally established.




Recommended Action

Approve Final Completion as submitted effective, August 20, 2008.



Financial Impact

None