School District of Clay County Green Cove Springs, Florida |
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway Hearings for Special Actions regarding Students - 4:00 p.m. REGULAR MEETING - 7:00 P.M. |
Agenda Item #43 Item Title C-43 Final Completion of Clay High School A/C Duct Board Replacement Issue/Rationale Establish a Final Completion date formally for audit purposes, and as required by the State Requirements for Education Facilities and The project, as determined by the Project Manager and Project Engineer (Kenyon & Partners, Inc.), has achieved Final Completion in accordance with the project documents. Liquidated damages are specified in the contract; therefore, a Final Completion date must be formally established. Recommended Action Approve Final Completion as submitted effective, August 20, 2008. Financial Impact None Submitted By Thomas L. Smith, Director of Maintenance |