School District of Clay County
Green Cove Springs, Florida
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway Hearings for Special Actions regarding Students - 4:00 p.m. REGULAR MEETING - 7:00 P.M.
October 16, 2008 Regular Meeting
Agenda Item #40


Item Title
C-40 Final Completion of Keystone Heights Elementary School Replacement of Transite Panels and Doors on East Wall Buildings 3, 4, 5, 6, 7 & 8

Issue/Rationale

Establish a Final Completion date formally for audit purposes, and as required by the State Requirements for Education Facilities and Florida Statutes. This date is determined by the Project Manager in accordance with Project documents. Final Completion was achieved on August 5, 2008.

 

The project, as determined by the Project Manager and Project Architect (SchenkelShultz Architecture), has achieved Final Completion in accordance with the project documents. Liquidated damages are specified in the contract; therefore, a Final Completion date must be formally established.



Recommended Action

Approve Final Completion as submitted effective, August 5, 2008.



Financial Impact

None



Submitted By

Thomas L. Smith, Director of Maintenance