C-30 Substantial and Final Completion of Lakeside Junior High School Building 5 Air Conditioner Replacement

Issue/Rationale

Establish Substantial and  Final Completion dates formally for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. These dates are determined by the Project Manager in accordance with project documents.  Substantial Completion was achieved on September 15, 2010 and Final Completion was achieved on September 30, 2010.

                               

The project, as determined by the Project Manager and Project Engineer (KPI Engineering, Inc.), is substantially and finally complete and in accordance with the project documents. Liquidated damages are specified in the contract; therefore, a substantial and final completion date must be formally established.  Contractor:  Hager Construction Company.



Recommended Action

Approve Substantial and Final Completion.



Financial Impact

None.



Submitted By

Michael J. Elliott, Assistant Superintendent of Support Services

 

Data Source:

 

Facility Planning and Construction




Attachment:  Sub Completion LJH HVAC.pdf