Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway OCTOBER 19, 2006 Hearings for Special Actions regarding Students - 4:00 p.m. REGULAR MEETING - 7:00 p.m.
October 19, 2006 Regular Meeting
Agenda Item #36


Item Title
C-37 Substantial Completion of Demolition (Phase I) at Charles E. Bennett Elementary School

Issue/Rationale

Establish a Substantial Completion date formally for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. This date is determined by the Project Manager in accordance with project documents.  Substantial Completion was achieved on September 25, 2006.

 

This phase of the project, as determined by the Project Manager and Project Architect (Bhide & Hall Architects, P.A.), is substantially complete and in accordance with the project documents. Liquidated damages are specified in the contract; therefore, a substantial completion date must be formally established.  Contractor:  M. M. Parrish Construction.



Recommended Action
Approve Substantial Completion.

Financial Impact

None.



Submitted By

James A. Connell, Director of Facility Planning and Construction