Agenda Item #39 Item Title C-27 Final Completion of Middleburg High School Fire Alarm Replacement Issue/Rationale Establish a Final Completion date for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. The Final Completion date is August 18, 2011. This phase of the project, as determined by the Project Manager and Project Architect/Engineer (KPI Engineering, Inc.), is finally complete and in accordance with the project documents. Contractor: T & M Electric, Inc. Recommended Action Approve Final Completion Financial Impact Submitted By James A. Connell, Assistant Superintendent for Support Services Data Source: Mike Griffis, Facility Planning and Construction Attachment: Final compl MHS Fire Alarm.pdf |