Item Title
C-30 Final Completion of Ridgeview High School Air Handling Unit Replacement Buildings 1 & 3

Issue/Rationale

Establish a Final Completion date for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. Final Completion was achieved on August 12, 2011.  The project, as determined by the Project Manager and Project Engineer (KPI Engineering, Inc.), has reached Final Completion in accordance with the project documents.



Recommended Action
Approve Final Completion

Financial Impact
None

Submitted By

James A. Connell, Assistant Superintendent for Support Services

 

Data Source:

 

Bryce Ellis, Facility Planning and Construction