September 15, 2011 Regular Meeting with Public Hearing on Budget
Agenda Item #40


Item Title
C-28 Final Completion of Montclair Elementary School Panelboard Replacement Buildings 1 - 3

Issue/Rationale

Establish a Final Completion date for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes.  The Final Completion date is August 15, 2011.  This phase of the project, as determined by the Project Manager and Project Architect/Engineer (KPI Engineering, Inc.), is finally complete and in accordance with the project documents.  Contractor:  Parks Electric Service, Inc.

 



Recommended Action

Approve Final Completion



Financial Impact
None

Submitted By

James A. Connell, Assistant Superintendent for Support Services

 

Data Source:

Mike Griffis, Facility Planning and Construction




Attachment:  Final compl MCE.pdf