School District of Clay County
Green Cove Springs, Florida
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway Hearings for Special Actions regarding Students - 5:00 p.m. REGULAR MEETING - 7:00 P.M.
September 16, 2010 Regular Meeting
Agenda Item #53


Item Title
C-43 Substantial and Final Completion of Tynes Elementary School Buildings 1 & 2 HVAC Replacement

Issue/Rationale

Establish Substantial and  Final Completion dates formally for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. These dates are determined by the Project Manager in accordance with project documents.  Substantial Completion was achieved on August 13, 2010 and Final Completion was achieved on August 18, 2010.

 

The project, as determined by the Project Manager and Project Engineer (KPI Engineering, Inc.), is substantially and finally complete and in accordance with the project documents. Liquidated damages are specified in the contract; therefore, a substantial and final completion date must be formally established.  Contractor:  Core Construction Company.

 



Recommended Action

Approve Substantial and Final Completion.



Financial Impact

None.



Submitted By

Michael J. Elliott, Assistant Superintendent of Support Services

 

Data Source:

Facility Planning and Construction




Attachment:  TES Sub Compl.pdf
Attachment:  TES Final Compl.pdf