School District of Clay County
Green Cove Springs, Florida
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway Hearing for Special Actions Regarding Students - 4:00 p.m. REGULAR MEETING - 7:00 p.m.
September 17, 2009 Regular Meeting with Public Hearing on Budget
Agenda Item #44


Item Title
C-32 Substantial and Final Completion of Orange Park High School Building 1, Renovate Down Spouts

Issue/Rationale

Establish a Substantial and Final Completion date formally for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. These dates are determined by the Project Manager in accordance with project documents.  Substantial Completion was achieved on August 14, 2009 and Final Completion was achieved on August 28, 2009.

 

The project, as determined by the Project Manager and Project Architect (McCullar & Boatright Architects, P.A.), is substantially and finally complete and in accordance with the project documents. Liquidated damages are specified in the contract; therefore, a substantial and final completion date must be formally established.  Contractor:  Hager Construction Company



Recommended Action

Approve Substantial and Final Completion.



Financial Impact

None



Submitted By

James A. Connell, Director of Facility Planning and Construction




Attachment:  Sub & Final Completion OPH Downspouts.pdf