Agenda Item #43 Item Title C-42 Substantial Completion of Clay High School Re-Roof Buildings 1 and 3 Issue/Rationale Establish a Substantial Completion date formally for audit purposes, and as required by the State Requirements for Education Facilities and The project, as determined by the Project Manager and Project Architect (McCullar & Boatright Architects), has achieved Substantial Completion in accordance with the project documents. Liquidated damages are specified in the contract; therefore, a Substantial Completion date must be formally established. Recommended Action Approve Substantial Completion as submitted effective, August 18, 2008. Financial Impact None Submitted By Thomas L. Smith, Director of Maintenance |