School District of Clay County Green Cove Springs, Florida |
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway Hearings for Special Actions regarding Students - 4:30 p.m. Regular Meeting - 7:00 p.m. |
Agenda Item #49 Item Title C-49 Final Completion of Lakeside Junior High School Fire Alarm Replacement Issue/Rationale Establish a Final Completion date formally for audit purposes, and as required by the State Requirements for Education Facilities and The project, as determined by the Project Manager and Project Engineer (Estrella Engineering Incorporated), has achieved Final Completion in accordance with the project documents. Liquidated damages are specified in the contract; therefore, a Final Completion date must be formally established. Recommended Action Approve Final Completion as submitted effective, September 1, 2008. Financial Impact None Submitted By Thomas L. Smith, Director of Maintenance |