School District of Clay County Green Cove Springs, Florida |
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway SEPTEMBER 21, 2006 Hearings for Special Actions regarding Students - 4:00 p.m. REGULAR MEETING - 7:00 p.m. |
Agenda Item #47 Item Title C-47 Fleming Island Elementary Permanent Classroom Addition Final Completion Issue/Rationale Establish a Final Completion date formally for audit purposes, and as required by the State Requirements for Educational Facilities and Florida Statutes. This date is determined by the Project Manager in accordance with project documents. The Final Completion date is August 17, 2006. The project, as determined by the Project Manager and Project Architect (McCullar & Boatright Architects, P.A.), is finally complete and in accordance with the project documents. Liquidated damages are specified in the contract; therefore, a final completion date must be formally established. Contractor: Thomas May Construction Company. Recommended Action Financial Impact None Submitted By James A. Connell, Director of Facility Planning and Construction Attachment: FIE Bldg 5 Final Comp.pdf |