Previous Item | Next Item |
|
||
April 2, 2020 - Regular School Board Meeting | ||
Title C26 - Change Order #1 for Keystone Heights High School Site Improvements (Sanitary Line) | ||
Description Change Orders are initiated by the Contractor, Architect/Engineer or Owner, and may increase or decrease the scope of the project as defined by the plans and specifications. Change Orders are reviewed by the Architect/Engineer and staff prior to submission to the School Board for approval. This change order is for emergency water line repair and credit air release valve that was deemed not needed. | ||
Gap Analysis N/A | ||
Previous Outcomes N/A | ||
Expected Outcomes Construction will proceed immediately translating to an on time completion. | ||
Strategic Plan Goal Ensure effective management of the organization, operations, and facilities to maximize the use of resources and promote a safe, efficient, and effective learning environment for Clay County students. | ||
Recommendation Approve Change Order # 1. | ||
Contact Dr. Michael Kemp, Assistant Superintendent for Operations, (904) 336-6824, michael.kemp@myoneclay.net, Bryce Ellis, Director of Facility Planning & Construction, (904) 336-6853, bryce.ellis@myoneclay.net | ||
Financial Impact This change order will increase the contract amount by $4,611.88. These funds are available and budgeted in the Educational Facilities Plan. | ||
Review Comments | ||
Attachments KHS Site Improvements CO 1.pdf |