Previous Item | Next Item |
|
||
April 4, 2024 - Regular School Board Meeting | ||
Title C36 - Substantial and Final Completion of Fleming Island High School Replace Batting Practice Building and Erosion Control | ||
Description Establish a Substantial and Final Completion date for audit purposes and as required by the State Requirements for Educational Facilities (SREF) and Florida Statutes. The project, as determined by the Project Manager and Project Architect/Engineer, has reached Substantial Completion on March 15, 2024 and Final Completion on March 15, 2024 in accordance with the project documents. | ||
Gap Analysis N/A | ||
Previous Outcomes N/A | ||
Expected Outcomes N/A | ||
Strategic Plan Goal Ensure fiscal responsibility through the effective management of district operations in an effort to maximize available resources necessary to provide an environment that is safe, efficient, and conducive to learning. | ||
Recommendation Approve Substantial and Final Completion. | ||
Contact Bryce Ellis, Assistant Superintendent for Operations, (904) 336-6853, bryce.ellis@myoneclay.net, Michael Kemp, Director of Facility Planning & Construction, (904) 336-6824, michael.kemp@myoneclay.net | ||
Financial Impact None. | ||
Review Comments | ||
Attachments FIH Batting Practice Building Substantial and Final Completion.pdf |