Title C19 - Change Order #3 for Green Cove Springs Junior High School Window/HVAC Replacement (Buildings 1, 2, & 3) | ||
Description Change Orders are initiated by the Contractor, Architect/Engineer or owner, and may increase or decrease the scope of the project as defined by the plans and specifications. Change Orders are reviewed by the Architect/Engineer or staff prior to submission to the School Board for approval. This Change Order is to extend existing home-run circuits and to provide/install conduit strapping for existing AC Circuit servicing classrooms 1, 3, 5, 7, and 9. | ||
Gap Analysis N/A | ||
Previous Outcomes N/A | ||
Expected Outcomes Construction will proceed immediately translating to an on time completion. | ||
Strategic Plan Goal Ensure fiscal responsibility through the effective management of district operations in an effort to maximize available resources necessary to provide an environment that is safe, efficient, and conducive to learning. | ||
Recommendation Approve Change Order #3. | ||
Contact Bryce Ellis, Assistant Superintendent for Operations, (904) 336-6853, bryce.ellis@myoneclay.net Lance Addison, Director for Facility Planning and Construction, (904) 336-6824, lance.addison@myoneclay.net | ||
Financial Impact This Change Order will increase the contract amount by $3,549.07. Architect fees will increase by $320.48. These funds are available and budgeted in the Educational Facilities Work Plan. | ||