Previous Item | Next Item |
|
||
February 6, 2025 - Regular School Board Meeting | ||
Title C21 - Substantial and Final Completion for Clay High School Track Improvements | ||
Description Establish a substantial completion and final completion date for audit purposes and as required by the State Requirements for Educational Facilities (SREF) and Florida Statutes. The project, as determined by the project manager and project architect/project contractor, has reached substantial completion on December 31, 2024 and final completion on January 16, 2025, in accordance with the project documents. | ||
Gap Analysis N/A | ||
Previous Outcomes N/A | ||
Expected Outcomes N/A | ||
Strategic Plan Goal Ensure fiscal responsibility through the effective management of district operations in an effort to maximize available resources necessary to provide an environment that is safe, efficient, and conducive to learning. | ||
Recommendation Approve Substantial and Final Completion. | ||
Contact Bryce Ellis, Assistant Superintendent for Operations, (904) 336-6853, bryce.ellis@myoneclay.net Lance Addison, Director of Facility Planning and Construction, (904) 336-6852, lance.addison@myoneclay.net | ||
Financial Impact None. | ||
Review Comments | ||
Attachments Certificate of Substantial Completion for CHS Track Improvements Certificate of Final Completion CHS Track Improvements |